Project Update - Week of December 4th, 2023

Please see the below project update and list of activities scheduled for the week of 12/4.

Jonathan May 0 69 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area. 
  • The general trades contractor will commence drywall of the classroom wing stairwell
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue initial coats of level 1 classrooms
  • The painting contractor will continue initial coats of the level 2 corridors
  • The ceiling contractor will continue ceiling grid on level 1 C. 
  • The ceiling contractor will continue ceiling grid install in the level 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C classrooms
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 A
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechanical contractor will prepare for initial roof top unit deliveries in December
  • The electrical contractor will continue overhead and in wall rough-in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A light fixtures
  • The tile contractor will continue grouting of level 2 single bathrooms
  • The tile contractor will continue level 2 corridor tile
  • The metal windows contractor will continue installation of the lobby skylights
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge

Project Update - Week of November 27th, 2023

Please see the below project update and list of activities scheduled for the week of 11/27.

Jonathan May 0 66 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A, Lobby and admin area. 
  • The general trades contractor will continue taping level 1 area D
  • The general trades contractor will continue insulation and drywall installation of the project areas and stair D
  • The painting contractor will continue initial coats of level 1 classrooms
  • The panting contractor will prime and paint the Platform exposed structure
  • The painting contractor will continue priming of the gym CMU
  • The ceiling contractor will continue ceiling grid on level 1 C. 
  • The ceiling contractor will commence ceiling grid install in the level 2 area C corridor
  • The millwork and casework contractor will commence casework installation on level 2 area C classrooms
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D and A
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough-in on level 1 area B cafeteria
  • The electrical contractor will continue installation of level 2 area c light fixtures
  • The electrical contractor will commence installation of level 2 area d light fixtures
  • The electrical contractor will commence level 2 toilet room light fixture install
  • The tile contractor will continue installation of level 2 single bathrooms
  • The elevator contractor will continue installation and assist other trades work within the elevator pit
  • The metal windows contractor will continue installation of the translucent panel in the gym and over the lobby
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge

Saturday Work - November 18th, 2023

The project will be working on the site this Saturday 11/18/23. Activities will consist of the following:

Jonathan May 0 78 Article rating: No rating
  • The mechanical contractor will continue VAV duct tie-in on level 1 D. 

Project Update - Week of November 20th, 2023

Please see the below project update and list of activities scheduled for the week of November 20th 2023

Jonathan May 0 75 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A
  • The general trades contractor will continue taping level 1 area D
  • The general trades contractor will commence drywall of the project areas and the stair D
  • The painting contractor will continue level 2 and level 1 classrooms
  • The panting contractor will prime and paint the Platform exposed structure
  • The ceiling contractor will continue ceiling grid on level 1 C
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The plumbing contractor will continue level 1 B in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D and A
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The mechanical contractor will commence duct tie-in to the roof curbs
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will continue installation of level 2 area c light fixtures
  • The electrical contractor will commence installation of level 2 area d light fixtures
  • The tile contractor will continue installation of level 2 single bathrooms
  • The elevator contractor will continue installation and assist other trades work within the elevator pit
  • The waterproofing contractor will commence waterproofing of the stem patio ceiling. 
  • The metal windows contractor will continue installation of the translucent panel in the gym
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge

Project Update - Week of November 13th, 2023

Please see the below project update and list of activities scheduled for the week of November 13th 2023

Jonathan May 0 82 Article rating: No rating
  • The metal panel contractor will continue the cafeteria canopy ceiling installation 
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A
  • The general trades contractor will continue taping level 1 area D
  • The painting contractor will continue level 2 and level 1 classrooms
  • The painting contractor will continue preperation of the gym CMU for paint
  • The ceiling contractor will commence ceiling grid on level 1
  • The fire protection contractor will continue overhead rough in of the exterior stem patio, cafeteria, and platform
  • The plumbing contractor will continue level 1 A in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will continue installation of level 2 lighting area C lighting fixtures
  • The tile contractor will continue installation of level 2 group bathroom floor and wall tile
  • The tile contractor will continue level 2 individual bathroom floor tile
  • The elevator contractor will continue installation and assist other trades work within the elevator pit