Please see the below project update and list of activities scheduled for the week of August 12th, 2024

  • The demolition contractor will demobilize from the site. 
  • The site contractor will continue preparation of the phase 2B concrete walks. 
  • The site contractor will continue subgrade preperation of the grade 1-4 playground and the basketball asphalt area. 
  • The paving contractor will pave the roadways. 
  • The concrete contractor will continue forming and pouring the phase 2B walkways. 
  • All contractors’ will continue addressing punchlist items. 