Saturday Work - November 9, 2024

The project will be working on the site this Saturday 11/9/24. Activities will consist of the following:

Jonathan May 0 14 Article rating: No rating
  • The fence contractor will continue installation of the playground fence. 
  • The landscape contractor will hydroseed the remaining lawn areas. 

Project Update - Week of November 11th, 2024

Please see the below project update and list of activities scheduled for the week of January 11th, 2024

Jonathan May 0 13 Article rating: No rating
  • The landscape contractor will hydroseeding of the demolition phase lawn areas and install the slope stabilization. 
  • The fence contractor will complete the remaining fence installation.

This completes the remaining landscape work for the season and will be the last project website update. 

Saturday Work - November 2nd, 2024

The project will be working on the site this Saturday 11/2/24. Activities will consist of the following:

Jonathan May 0 19 Article rating: No rating
  • The site contractor will complete top coat paving of the campus's main entrance road. 
  • The landscape contractor will commence the parking lot stone edge installation. 

Project Update - Week of November 4th, 2024

Please see the below project update and list of activities scheduled for the week of November 4th, 2024.

Jonathan May 0 19 Article rating: No rating
  • The landscape contractor will continue fence installation, final irrigation connections & programming, and commence hydroseeding the perimeter lawn areas. 
  • The electrical contractor will wire and set the entrance light pole. 
  • The concrete contractor will form and pour the remaining perimeter concrete walks. 

Project Update - Week of October 28th, 2024

Please see the below project update and list of activities scheduled for the week of October 28th, 2024

Jonathan May 0 21 Article rating: No rating
  • The site contractor will continue with the construction entrance re-establishment. 
  • The site contractor will continue with entrance road utility frame and cover adjustments ahead of final paving. 
  • The landscape contractor will commence placing sod, continue fence installation, and continue irrigation installation. 