Project Update - Week of September 26th 2022

Jonathan May 0 4 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 26th 2022. 

  • The track surface contractor will finalize layout and commence the track surface installation.
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of Area B. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.

 

Project Update - Week of September 19th 2022

Jonathan May 0 19 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 19th 2022. 

  • The irrigation with complete final position of irrigation heads. 
  • The track surface contractor will begin placing of the synthetic track surface. 
  • The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. 
  • The concrete contractor will continue forming and placing concrete foundations in Areas A & B.  
  • Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D.  
  • The site contractor will continue foundation excavation of Areas A & B. 
  • The site contractor will continue utility installation below the proposed perimeter access road.
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of August 29th 2022

Jonathan May 0 34 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/29.

  • Exporting excess materials from the site shall continue this week.   
  • The fencing contractor will complete the athletic field retaining wall fence installation. 
  • The irrigation system will be completed
  • The drainage structure covers will be installed
  • The electrical contractor will commence providing power to the new athletic field shed location 
  • The concrete contractor will continue foundation construction for the classroom wings Area C & D. 
  • The site contractor will continue to excavate the Area A & B foundations. 
  • The electrical and site contractors will continue the electrical ductbank installation down Champney Street. 
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of May 13th 2022

Please see the below project update and list of activities scheduled for the week of 5/16.

Jonathan May 0 128 Article rating: 5.0
  • Complete Con-Com and Stormwater Agent inspection of erosion control measures. 
  • The site contractor will begin stripping topsoil at the new track & field location.
  • The site contractor will begin demolition of existing field equipment, fencing, benches, etc.
  • Electrical and plumbing contractors will complete the construction trailer electrical and plumbing hookups. 

 

Project Update - Week of May 6th 2022

Please see the below project update and list of activities scheduled for the week of 5/9.

Jonathan May 0 91 Article rating: 5.0
  • The fence contractor will complete the driven post and fence installation.
  • The site contractor will complete the installation of erosion control measures along the perimeter of the construction site. 
  • The project will conduct the perimeter erosion control and SWPPP inspections with the town Conservation Committee Inspector and the Storm Water Advisory Agent.  
  • The site contractor will complete the implementation of the temporary construction access road. 
  • The site contractor will also mobilize additional earth moving equipment. 
RSS
12

Theme picker