Saturday Work - March 23, 2024

The project will be working on the site this Saturday 3/23/24. Activities will consist of the following:

Jonathan May 0 9 Article rating: No rating
  • The painting contractor will focus on caulking of the level 2 windows.

Project Update - Week of March 25th, 2024

Please see the below project update and list of activities scheduled for the week of March 25th, 2024

Jonathan May 0 8 Article rating: No rating
  • The site contractor will continue the outdoor learning lab site preperation. 
  • The general trades contrctor will continue installation of interior and exterior expansion joints. 
  • The waterproofing contrator will continue caulking of exterior masonry and metal panel joints. 
  • The concrete contractor will continue forming the front entrance stair foundations and outdoor learning lab concrete sidewalks. 
  • The masonry contractor will continue erecting the final masonry elevation at the project's loading and trashout area. 
  • The general trades contractor will continue  level 1 door and hardware installation. 
  • The general trades contractor will continue taping of stair A closure walls. 
  • The resilient flooring contractor will continue the level 2 corridor flooring and commence level 1 corridor. 
  • The painting contractor will continue final painting of the level 2 area C classrooms.
  • The painting contractor will continue final caulking of all windows.  
  • The ceiling contractor will continue kitchen and lobby ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will install the RTU catwalks.
  • The mechanical contractor will install the radiant heat panels in the lobby. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will continue initial inspections and testing of the fire alarm system. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet partitions. 
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will commence the kitchen floor installation. 
  • The shade contractor will commence shade installation in the level 2 classrooms. 
  • The gym flooring contractor will commence the gym subfloor installation. 

Saturday Work - March 9th, 2024

The project will be working on the site this Saturday 3/9/24. Activities will consist of the following:

Jonathan May 0 18 Article rating: No rating
  • The electrical contractor will work with GELD to energize the project's permenant electrical service. 

Project Update - Week of March 11th, 2024

Please see the below project update and list of activities scheduled for the week of March 11th, 2024

Jonathan May 0 16 Article rating: No rating
  • The general trades contractor will continue installation of level 2 and commence level 1 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. 
  • The general trades contractor will frame & drywall the main stair knee wall ahead of floor finishes. 
  • The resilient flooring contractor will continue the level 2 corridor flooring. 
  • The painting contractor will continue final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue cafeteria and kitchen ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The millwork and casework contractor will commence the stem patio cubby installation. 
  • The plumbing contractor will continue level 1 classroom sink installation. 
  • The plumbing and mechanical contractor will continue installing valve tags on level 2. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue installing the cafeteria wall diffusers. 
  • The mechanical contractor will install the gym fan blades. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will commence energizing electrical panels supported by permenant power. 
  • The electrical contractor will continue fire alarm finish installation on level 1. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will commence the cafeteria wall tile.
  • The specialties contractor will continue installation of the toilet partitions. 
  • The site contractor will commence courtyard sitework preperation. 
  • The waterproofing and masonry contractor will re-mobilize to close in the project's level 2 loadout elevation. 
  • The misc. metals contractor will commence installation of the main stair railings. 

Project Update - Week of March 4th, 2024

Please see the below project update and list of activities scheduled for the week of March 4th, 2024

Jonathan May 0 27 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. 
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The resilient flooring contractor will commence the level 2 area D corridor flooring. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The painting contractor will continue final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, cafeteria, and lobby.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation.
  • The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. 
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will commence level 1 classroom sink installation. 
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The plumbing and mechanical contractor will continue installing valve tags on level 2. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue installing the cafeteria wall diffusers. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The electrical contractor will continue making final electrical wiringing connections in the main electric room. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. 