Project Update Week of March 13th 2023 Please see the below project update and list of activities scheduled for the week of March 13th 2023 Jonathan May / Sunday, March 12, 2023 0 17 Article rating: No rating The site contractor will begin the installation of drainage infilitration system IT-2 on the South-West side of the site. The general trades contractor shall continue with the lay-out and installation of roof blocking. The general trades contractor will continue framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C, D, & A. The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas. The plumbing contractor will continue to layout roof and level 2 openings as well as install level 2 slab on deck sleeves. The building electrical contractor will continue layout and installation of underslab electrical and telecommunications conduit. Read more
Project Update - Week of March 6th 2023 Please see the below project update and list of activities scheduled for the week of March 6th 2023 Jonathan May / Saturday, March 4, 2023 0 19 Article rating: No rating The site contractor will continue with the installation of drainage infilitration system IT-1A on the South-West side of the site. The general trades contractor shall continue with the lay-out and installation of roof blocking. The general trades contractor shall commence with framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C & D of the building. The concrete contractor shall continue and complete forming and placing the reverse isolation boxes located in the slabs on grade of the building this week. Concrete placements will be weather-temperature dependant. The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas. The roofing contractor will continue installation of various roof AVB details needed to support the continuation of roof blocking activities. The building electrical contractor will mobilize to site and layout and installation of underslab electrical and telecommunications conduit. Read more
Project Update - Week of December 19th 2022 Please see the below project update and list of activities scheduled for the week of December 19th 2022 Jonathan May / Friday, December 16, 2022 0 50 Article rating: No rating The electrical enabling contractor shall complete permanent power conduit installation to the main electric room. The site contractor shall continue with the excavation and installation of the new drainage line and structures along the projects site access road. The structural steel contractor will mobilize to site and begin receiving steel deliveries. The structural steel contractor shall commence steel erection of the Area C Classroom Wing. Read more
Project Update - Week of October 11th 2022 Jonathan May / Friday, October 7, 2022 0 73 Article rating: No rating Please see the below project update and list of activities scheduled for the week of October 11th 2022. The athletic track line stripper will commence track markings. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas B. The site contractor will commence loading dock footing backfill. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The site contractor will continue underslab plumbing excavation. The site contractor will prep and set the BESS system vault and transformer pad. The concrete contractor will continue forming and placing the loading dock and site wall foundation. The concrete contractor will continue pouring the interior gym strip footing. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. The plumbing enabling contractor will continue layout and installation of the underslab plumbing in Area C. Read more
Project Update - Week of October 3rd 2022 Jonathan May / Friday, September 30, 2022 0 76 Article rating: No rating Please see the below project update and list of activities scheduled for the week of October 3rd 2022. The track surface contractor will continue the track surface installation The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B. The site contractor will continue foundation excavation of the Area B site wall, the loading dock, and the gym interior strip footing. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The site contractor will begin building underslab plumbing excavation. The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. The concrete contractor will begin forming and installing rebar for the loading dock deep footing. The concrete contractor will continue pouring the interior gym strip footing. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. The plumbing enabling contractor will begin layout and installation of the underslab plumbing in Area C. Read more