Jonathan May / Friday, August 18, 2023 / Categories: Uncategorized Project Update - Week of August 21st, 2023 Please see the below project update and list of activities scheduled for the week of August 21st, 2023 The waterproofing contractor will continue waterproofing of the storefront openings. The masonry contractor will masonry installation on the area B west elevation. The window contractor will continue window installation in area A. The roofing contractor will continue instllation of the metel roof edge. The metal panel contractor will continue metal panel installation on the outdoor learning lab elevations. The concrete contractor will continue layout and installtion of formwork for interior equipment pads and elevated slabs. The general trades contractor will continue insulation and drywall installation on level 2 C&D as well as the remaining electric rooms on level 1. The painting contractor will continue painting of the electric rooms in preperation for the electrical contractor's buildout. The electrical contractor will continue build out of the level 2 and level 1 electrical room buildout including the main electric room. The electrical contractor will continue in wall rough-in on level 1 areas C & D. The mechanical contractor will continue duct installation on level 1 area D & A. The mechanical contractor will continue displacement diffuser installation on level 1. The mechanical and plumbing contractor will continue insulation installation for pipe and ductwork. The mechanical contractor will continue in-wall rough-in of mechanical control devices on level 1. The mechanical contracotr will continue mechanical room equipment setting and tie-in of piping. The fire protection contractor will continue overhead installation of sprinkler pipe on level 1 area A. The plumbing contractor will continue in-wall rough-in on level 1 areas C & D. Previous Article Saturday Work - August 12th 2023 Next Article Saturday Work - August 19th, 2023 Print 255 Rate this article: No rating