Jonathan May / Thursday, August 24, 2023 / Categories: Uncategorized Project Update - Week of August 28th, 2023 Please see the below project update and list of activities scheduled for the week of August 28th, 2023 The metal panel contractor will continue installation of the the Area D metal panel bump out. The window contractor will continue waterproofing of the window systems. The window contractor will continue window installation on level 2 A. The roofing contractor will continue installation metal roof edge install and low roof roofing system install. The general trades contractor will complete the low roof and main canopy roof edge blocking. The general trades contractor continue level 2 area A perimeter wall insulation. The general trades contractor will continue drywall installation on level 2 area D & A. The general trades contractor will continue in-wall blocking installation on level 1 C. the general trades contractor will continue taping in level 2 area C. The electrical contractor will continue electrical room build-out. The electrical contractor continue in-wall electrical rough-in on level 1 area D. The fire protection contractor will continue sprinkler pipe rough-in on level 1 area A & B. The mechanical contractor will continue overhead duct installation on level 1 Area A. The mechanical contractor will continue in-wall duct installation on level 2 area B and level 1 area C. The mechanical controls contractor will continue in-wall rough-in on level 1 area C & D. The mechanical and plumbing contractors will continue mechanical room build-out. The plumbing contractor will continue plumbing pipe installation on level 1 area A. The concrete contractor will continue preperation and pouring of the platform and stair B subfloor concrete stairs. Previous Article Saturday Work - August 19th, 2023 Next Article Saturday Work - August 26th, 2023 Print 242 Rate this article: No rating