Jonathan May / Saturday, August 27, 2022 / Categories: Uncategorized Project Update - Week of August 29th 2022 Exporting excess materials from the site shall continue this week. The fencing contractor will complete the athletic field retaining wall fence installation. The irrigation system will be completed The drainage structure covers will be installed The electrical contractor will commence providing power to the new athletic field shed location The concrete contractor will continue forming & placing concrete for the classroom wing foundations. The site contractor will continue to excavate the Area A & B foundations. The electrical and site contractors will continue the electrical ductbank installation down Champney Street. The site contractor will continue various grading activities around the site. Previous Article Project Update - Week of August 22nd 2022 Next Article Project Update - Week of September 5th 2022 Print 348 Rate this article: No rating