Project Update - Week of August 7th, 2023

Please see the below project update and list of activities scheduled for the week of August 7th, 2023.

  • The general trades contractor will continue drywall and taping of the level 2 area C & D electric rooms.
  • The general trades contractor will continue interior framing on level 1 areas C & D.
  • The general trades contractor will commence interior drywall and insulation on level 2 C.
  • The concrete contractor will form and place the Stair B elevated slab.
  • The concrete contractor will form and place the platform stairs and ramps.
  • The concrete contractor will pour the main electric room slab on grade.
  • The mechanical contractor will continue duct installation on level 1 D & A.
  • The mechanical contractor will continue duct insulation install on level 2.
  • The plumbing contractor will continue in-wall rough in on level 1 C
  • The plumbing contractor will continue gas pipe installation on level 1.
  • The plumbing contractor will commence roof drain tie-in in the gym.
  • The roofing contractor will continue roof edge metal installation.
  • The electrical contractor will continue in-wall rough in on level 2 A and level 1 C.
  • The electrical contractor will continue buildout of the level 2 area C & D electrical rooms.
  • The fireproofing contractor will continue sprinkler pipe installation on level 1 A & B.
  • The masonry contractor will continue masonry veneer installation on A & B exterior elevations.
  • The waterproofing contractor will continue waterproofing membrane on the west elevation of area A & B.
  • The metal panel contractor will continue panel installation on area C & D east bump outs.
  • The metal windows contractor will continue window installation on level 2 A & B.
Previous Article Saturday Work - July 29th 2023