Jonathan May / Friday, August 4, 2023 / Categories: Uncategorized Project Update - Week of August 7th, 2023 Please see the below project update and list of activities scheduled for the week of August 7th, 2023. The general trades contractor will continue drywall and taping of the level 2 area C & D electric rooms. The general trades contractor will continue interior framing on level 1 areas C & D. The general trades contractor will commence interior drywall and insulation on level 2 C. The concrete contractor will form and place the Stair B elevated slab. The concrete contractor will form and place the platform stairs and ramps. The concrete contractor will pour the main electric room slab on grade. The mechanical contractor will continue duct installation on level 1 D & A. The mechanical contractor will continue duct insulation install on level 2. The plumbing contractor will continue in-wall rough in on level 1 C The plumbing contractor will continue gas pipe installation on level 1. The plumbing contractor will commence roof drain tie-in in the gym. The roofing contractor will continue roof edge metal installation. The electrical contractor will continue in-wall rough in on level 2 A and level 1 C. The electrical contractor will continue buildout of the level 2 area C & D electrical rooms. The fireproofing contractor will continue sprinkler pipe installation on level 1 A & B. The masonry contractor will continue masonry veneer installation on A & B exterior elevations. The waterproofing contractor will continue waterproofing membrane on the west elevation of area A & B. The metal panel contractor will continue panel installation on area C & D east bump outs. The metal windows contractor will continue window installation on level 2 A & B. Previous Article Saturday Work - July 29th 2023 Next Article Saturday Work - August 5th 2023 Print 228 Rate this article: No rating