Jonathan May / Thursday, December 7, 2023 / Categories: Uncategorized Project Update - Week of December 11, 2023 Please see the below project update and list of activities scheduled for the week of December 11th, 2023 The general trades contractor will continue metal framing activities in the cafeteria and kitchen The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area. The general trades contractor will commence drywall of the classroom wing stairwell The general trades contractor will commence drywall installation in the cafeteria and media center The general trades contractor will continue in-wall blocking and drywall installation in the media center The general trades contractor will continue taping level 1 area D and A The painting contractor will continue initial coats of level 1 classrooms The ceiling contractor will commence ceiling grid on level 1 C. The ceiling contractor will continue ceiling grid install in the level 2 area C corridor The millwork and casework contractor will continue casework installation on level 2 area C classrooms and commence area D classrooms The fire protection contractor will continue overhead rough in of the cafeteria and platform The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install The mechanical contractor will continue duct installation in the gym The mechanical contractor will continue setting radiant panels into completed ceiling grid The mechanical contractor will receive the first delivery of roof top units. The mechancial contractor will commence overhead duct rough-in in the cafeteria & lobby The electrical contractor will continue overhead and in wall rough-in on level 1 area B cafeteria The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C light fixtures The tile contractor will continue level 2 corridor tile The tile contractor will commence level 1 group bathroom floor and wall tile preperation. The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge The metal windows contractor will continue installation of the courtyard storefronts Previous Article Saturday Work - December 9th, 2023 Next Article Saturday Work - December 16th, 2023 Print 185 Rate this article: No rating