Project Update - Week of February 12th, 20234

Please see the below project update and list of activities scheduled for the week of February 12th, 2024

  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will continue stair A drywall and taping.
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will commence level 1 area D classroom and corridor casework installation.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The mechanical contractor will continue final duct connections to the roof top units received last week. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 1 corridor tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue tectum panel install in the gymnasium. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 classrooms. 