Jonathan May / Friday, February 9, 2024 / Categories: Uncategorized Project Update - Week of February 12th, 20234 Please see the below project update and list of activities scheduled for the week of February 12th, 2024 The general trades contractor will continue installation of level 2 doors and hardware. The general trades contractor will continue stair A drywall and taping. The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will commence level 1 area D classroom and corridor casework installation. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will continue final plumbing connections in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue setting radiant panels into completed ceiling grid. The mechanical contractor will continue final duct connections to the roof top units received last week. The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. The electrical contractor will continue fire alarm finish installation on level 1. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The tile contractor will continue level 1 corridor tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The specialties contractor will continue tectum panel install in the gymnasium. The specialties contractor will continue markerboard and tack board installation in the level 2 classrooms. Previous Article Saturday Work - February 3rd, 2024 Next Article Project Update - Week of February 20th, 2024 Print 191 Rate this article: No rating