Jonathan May / Friday, July 7, 2023 / Categories: Uncategorized Project Update - Week of July 10th 2023 Please see the below project update and list of activities scheduled for the week of July 10th 2023 The general trades contractor will continue exterior framing & sheathing in Areas A & B. The general trades contractor will continue layout and interior framing on level 2 Areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas A & B The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will continue installation of fire protection pipe on Level 1 Area C. The window contractor will continue with installation of the metal windows in Area C & D. Previous Article Project Update - Week of July 3rd 2023 Next Article Saturday Work - July 8th, 2023 Print 233 Rate this article: No rating