Project Update - Week of July 24th, 2023

Please see the below project update and list of activities scheduled for the week of July 24th 2023.

  • The general trades contractor will complete exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B and Level 1 C. 
  • The general trades contractor will commence level 2 C and D wood blocking installation. 
  • The waterproofing contractor will continue waterproofing Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas A & B
  • The masonry contractor will complete the gymnasium CMU wall. 
  • The concrete contractor will place the stage platform concrete stairs. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The mechanical contractor will continue installation of in-wall duct drops to displacement diffusers and installation of duct insulation. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing on Level 2 Areas D & A, and Level 1 Area D. 
  • The plumbing contractor will commence gas line installation in the mechanical room. 
  • The electrical contractor will continue in-wall rough-in on level 2 D. 
  • The electrical contractor will continue the build out of the level 2 electrical rooms. 
  • The electrical contractor will continue overhead rough-in on level 1. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 1 Area D. 
  • The window contractor will continue with installation of the metal windows in Area D.
  • The metal panel contractor will continue installation of the exterior metal panel system on areas C&D facade. 