Jonathan May / Monday, June 5, 2023 / Categories: Uncategorized Project Update - Week of June 6th, 2023 Please see the below project update and list of activities scheduled for the week of June 6th, 2023. The sitework contractor will commence preperation of the Slab on Grade in Area A and the Gym The general trades contractor will continue exterior framing in areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. The masonry contractor will continue installation of masonry veneer in areas C & D. The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. The mechanical contractor will continue installation of overhead mechanical duct and pipping in level 2 A and level 1 C & D. The plumbing contractor will continue installation of overhead and in-wall plumbing piping in level 2 C, D, & A, and level 1 C. The electrical contractor will continue installation of temporary lighting in the Gym. The electrical contractor will continue installation of overhead rough-in on level 2 A and in-wall rough-in on level 2 C&D. The fire protection contractor will continue installation of fire protection pipe on level 2. Previous Article Project Update - Week of May 22nd 2023 Next Article Project Update - Week of June 12th, 2023 Print 245 Rate this article: No rating