Jonathan May
/ Categories: Uncategorized

Project Update - Week of June 6th, 2023

Please see the below project update and list of activities scheduled for the week of June 6th, 2023.

  • The sitework contractor will commence preperation of the Slab on Grade in Area A and the Gym
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of masonry veneer in areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and pipping in level 2 A and level 1 C & D. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping in level 2 C, D, & A, and level 1 C. 
  • The electrical contractor will continue installation of temporary lighting in the Gym. 
  • The electrical contractor will continue installation of overhead rough-in on level 2 A and in-wall rough-in on level 2 C&D. 
  • The fire protection contractor will continue installation of fire protection pipe on level 2.
Previous Article Project Update - Week of May 22nd 2023
Next Article Project Update - Week of June 12th, 2023
Print
156 Rate this article:
No rating

Theme picker