Jonathan May
/ Categories: Uncategorized

Project Update Week of March 13th 2023

Please see the below project update and list of activities scheduled for the week of March 13th 2023

  • The site contractor will begin the installation of drainage infilitration system IT-2 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking.
  • The general trades contractor will continue framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C, D, & A.
  • The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas.
  • The plumbing contractor will continue to layout roof and level 2 openings as well as install level 2 slab on deck sleeves. 
  • The building electrical contractor will continue layout and installation of underslab electrical and telecommunications conduit. 
Previous Article Project Update - Week of March 6th 2023
Next Article Project Update - Week of March 20th 2023
Print
176 Rate this article:
No rating

Theme picker