Jonathan May
/ Categories: Uncategorized

Project Update - Week of March 25th, 2024

Please see the below project update and list of activities scheduled for the week of March 25th, 2024

  • The site contractor will continue the outdoor learning lab site preperation. 
  • The general trades contrctor will continue installation of interior and exterior expansion joints. 
  • The waterproofing contrator will continue caulking of exterior masonry and metal panel joints. 
  • The concrete contractor will continue forming the front entrance stair foundations and outdoor learning lab concrete sidewalks. 
  • The masonry contractor will continue erecting the final masonry elevation at the project's loading and trashout area. 
  • The general trades contractor will continue  level 1 door and hardware installation. 
  • The general trades contractor will continue taping of stair A closure walls. 
  • The resilient flooring contractor will continue the level 2 corridor flooring and commence level 1 corridor. 
  • The painting contractor will continue final painting of the level 2 area C classrooms.
  • The painting contractor will continue final caulking of all windows.  
  • The ceiling contractor will continue kitchen and lobby ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will install the RTU catwalks.
  • The mechanical contractor will install the radiant heat panels in the lobby. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will continue initial inspections and testing of the fire alarm system. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet partitions. 
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will commence the kitchen floor installation. 
  • The shade contractor will commence shade installation in the level 2 classrooms. 
  • The gym flooring contractor will commence the gym subfloor installation. 
Previous Article Saturday Work - March 9th, 2024
Next Article Saturday Work - March 23, 2024
Print
40 Rate this article:
No rating

Theme picker