Jonathan May / Friday, March 22, 2024 / Categories: Uncategorized Project Update - Week of March 25th, 2024 Please see the below project update and list of activities scheduled for the week of March 25th, 2024 The site contractor will continue the outdoor learning lab site preperation. The general trades contrctor will continue installation of interior and exterior expansion joints. The waterproofing contrator will continue caulking of exterior masonry and metal panel joints. The concrete contractor will continue forming the front entrance stair foundations and outdoor learning lab concrete sidewalks. The masonry contractor will continue erecting the final masonry elevation at the project's loading and trashout area. The general trades contractor will continue level 1 door and hardware installation. The general trades contractor will continue taping of stair A closure walls. The resilient flooring contractor will continue the level 2 corridor flooring and commence level 1 corridor. The painting contractor will continue final painting of the level 2 area C classrooms. The painting contractor will continue final caulking of all windows. The ceiling contractor will continue kitchen and lobby ceiling installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 admin area casework install. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will install the RTU catwalks. The mechanical contractor will install the radiant heat panels in the lobby. The electrical contractor will continue installation of the lobby and kitchen light fixtures. The electrical contractor will continue initial inspections and testing of the fire alarm system. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will commence the kitchen floor installation. The shade contractor will commence shade installation in the level 2 classrooms. The gym flooring contractor will commence the gym subfloor installation. Previous Article Saturday Work - March 9th, 2024 Next Article Saturday Work - March 23, 2024 Print 164 Rate this article: No rating