Project Update - Week of April 1st, 2024

Please see the below project update and list of activities scheduled for the week of April 1st, 2024

  • The site contractor will continue the outdoor learning lab site preparation and commence the perimeter road landscape area preparation. 
  • The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. 
  • The general trades contractor will commence metal framing of the outdoor stem patio ceiling. 
  • The concrete contractor will commence forming of the outdoor learning lab exterior flatwork. 
  • The general trades contractor will continue level 1 door and hardware installation. 
  • The resilient flooring contractor will continue the level 1 corridor flooring.
  • The painting contractor will continue final painting of the level 2. 
  • The painting contractor will continue final caulking of all windows.
  • The ceiling contractor will continue the lobby ceiling grid and panel installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The millwork and casework contractor will commence installation of the cafeteria acoustic panels. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will install the RTU catwalks.
  • The mechanical contractor will install the radiant heat panels in the lobby. 
  • The mechanical contractor will continue with initial factory startup of the RTUs. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The electrical contractor will continue installation of the lobby light fixtures. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet accessories and partitions.
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will continue the kitchen floor installation. 
  • The shade contractor will continue shade installation in the level 2 classrooms. 
  • The gym flooring contractor will continue the gym floor installation. 