Jonathan May / Friday, March 29, 2024 / Categories: Uncategorized Project Update - Week of April 1st, 2024 Please see the below project update and list of activities scheduled for the week of April 1st, 2024 The site contractor will continue the outdoor learning lab site preparation and commence the perimeter road landscape area preparation. The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. The general trades contractor will commence metal framing of the outdoor stem patio ceiling. The concrete contractor will commence forming of the outdoor learning lab exterior flatwork. The general trades contractor will continue level 1 door and hardware installation. The resilient flooring contractor will continue the level 1 corridor flooring. The painting contractor will continue final painting of the level 2. The painting contractor will continue final caulking of all windows. The ceiling contractor will continue the lobby ceiling grid and panel installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1. The millwork and casework contractor will continue level 1 admin area casework install. The millwork and casework contractor will commence installation of the cafeteria acoustic panels. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will install the RTU catwalks. The mechanical contractor will install the radiant heat panels in the lobby. The mechanical contractor will continue with initial factory startup of the RTUs. The controls contractor will continue integrating equipment into the building management system. The electrical contractor will continue installation of the lobby light fixtures. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet accessories and partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will continue the kitchen floor installation. The shade contractor will continue shade installation in the level 2 classrooms. The gym flooring contractor will continue the gym floor installation. Previous Article Saturday Work - March 23, 2024 Next Article Project Update - Week of April 8th, 2024 Print 166 Rate this article: No rating