Jonathan May / Friday, April 5, 2024 / Categories: Uncategorized Project Update - Week of April 8th, 2024 Please see the below project update and list of activities scheduled for the week of April 8th, 2024 The site contractor will continue preperation of the perimeter road landscape area and the rain garden. The concrete contractor will continue setting expansion joints for the outdoor learning lab concrete. The concrete contractor will continue forming of the front entrance CIP stairs. The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. The general trades contractor will continue metal framing of the outdoor stem patio ceiling. The general trades contractor will continue level 1 door and hardware installation. The resilient flooring contractor will continue the level 1 corridor flooring. The painting contractor will continue final painting of the level 2. The painting contractor will continue final caulking of all windows. The painting contractor will continue painting of level 1. The ceiling contractor will continue the lobby ceiling grid and panel installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1. The millwork and casework contractor will commence installation of the cafeteria acoustic panels. The millwork and casework contractor will commence the platform subfloor installation and the media center seating. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will continue with project commissioning. The controls contractor will continue integrating equipment into the building management system. The electrical contractor will continue installation of the lobby light fixtures. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet accessories and partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will continue the kitchen floor installation. The shade contractor will continue shade installation in the level 1 classrooms. Previous Article Project Update - Week of April 1st, 2024 Next Article Saturday Work - April 6th, 2024 Print 149 Rate this article: No rating