Jonathan May / Friday, August 23, 2024 / Categories: Uncategorized Project Update - Week of August 26th, 2024 Please see the below project update and list of activities scheduled for the week of August 26th, 2024 The site contractor will continue preparation of the final landscape area lawns. The site contractor will commence site lighting conduit routes & setting light pole bases. The landscape contractor will continue subgrade preparation of the basketball court & the playground area. The landscape contractor will commence initial paving course of the basketball court. The concrete contractor will continue forming and pouring the remaining walkways. The FloRo students will return to class for the 2024-2025 school year!!! Previous Article Project Update - Week of August 19th, 2024 Next Article Project Update - Week of September 9th, 2024 Print 88 Rate this article: 5.0