Please see the below project update and list of activities scheduled for the week of September 9th, 2024

  • The site contractor will continue setting final grade of the front lawn area. 
  • The site contractor will continue setting light pole bases on the north side of the lawn area. 
  • The electrical contractor will continue site lighting conduit and wire installation. 
  • The landscape contractor will continue the basketball fence installation. 
  • The landscape and concrete contractor will continue pouring the playground perimeter concrete curb. 
  • The landscape contractor will continue subgrade preparation of the playground and planting areas. 