Jonathan May / Friday, September 6, 2024 / Categories: Uncategorized Project Update - Week of September 9th, 2024 Please see the below project update and list of activities scheduled for the week of September 9th, 2024 The site contractor will continue setting final grade of the front lawn area. The site contractor will continue setting light pole bases on the north side of the lawn area. The electrical contractor will continue site lighting conduit and wire installation. The landscape contractor will continue the basketball fence installation. The landscape and concrete contractor will continue pouring the playground perimeter concrete curb. The landscape contractor will continue subgrade preparation of the playground and planting areas. Previous Article Project Update - Week of August 26th, 2024 Next Article Project Update - Week of September 16th, 2024 Print 70 Rate this article: 5.0