Jonathan May
/ Categories: Uncategorized

Project Update - Week of December 18th 2022

Please see the below project update and list of activities scheduled for the week of December 18th 2023

  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area
  • The general trades contractor will continue drywall of the classroom wing stairwell
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 1 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C and D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechancial contractor will continue overhead duct rough-in in the platform
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C/D light fixtures. 
  • The electrical contractor will commence installing the level 2 area C corridor light fixtures
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 
Previous Article Saturday Work - December 16th, 2023
Next Article Project Update - Week of December 26th, 2023
Print
195 Rate this article:
No rating

Theme picker