Jonathan May / Friday, December 15, 2023 / Categories: Uncategorized Project Update - Week of December 18th 2022 Please see the below project update and list of activities scheduled for the week of December 18th 2023 The general trades contractor will continue hanging drywall in the cafeteria and media center The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area The general trades contractor will continue drywall of the classroom wing stairwell The general trades contractor will continue in-wall blocking and drywall installation in the media center The general trades contractor will continue taping level 1 area D and A The painting contractor will continue painting of level 1 classrooms and corridors The ceiling contractor will continue ceiling grid on level 1 2 area C corridor The millwork and casework contractor will continue casework installation on level 2 area C and D classrooms. The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install The mechanical contractor will continue duct installation in the gym The mechanical contractor will continue setting radiant panels into completed ceiling grid The mechancial contractor will continue overhead duct rough-in in the platform The electrical contractor will continue overhead rough in on level 1 area B cafeteria The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C/D light fixtures. The electrical contractor will commence installing the level 2 area C corridor light fixtures The tile contractor will continue level 2 corridor tile The tile contractor will continue level 1 group bathroom floor and wall tile preperation. Previous Article Saturday Work - December 16th, 2023 Next Article Project Update - Week of December 26th, 2023 Print 195 Rate this article: No rating