Project Update - Week of December 26th, 2023

Please see the below project update and list of activities scheduled for the week of December 26th 2023

  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will commence drywall of the Stair D
  • The general trades contractor will continue taping level 1 area A & B
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors
  • The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation
  • The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 
  • The resilient flooring contractor will continue floor tile installation on level 2 area C classrooms