Jonathan May / Saturday, December 23, 2023 / Categories: Uncategorized Project Update - Week of December 26th, 2023 Please see the below project update and list of activities scheduled for the week of December 26th 2023 The general trades contractor will continue hanging drywall in the cafeteria and media center The general trades contractor will commence drywall of the Stair D The general trades contractor will continue taping level 1 area A & B The painting contractor will continue painting of level 1 classrooms and corridors The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms. The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform The mechanical contractor will continue setting radiant panels into completed ceiling grid The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. The tile contractor will continue level 2 corridor tile The tile contractor will continue level 1 group bathroom floor and wall tile preperation. The resilient flooring contractor will continue floor tile installation on level 2 area C classrooms Previous Article Project Update - Week of December 18th 2022 Next Article Project Update - Week of January 2nd, 2024 Print 215 Rate this article: No rating