Jonathan May
/ Categories: Uncategorized

Project Update - Week of December 4th, 2023

Please see the below project update and list of activities scheduled for the week of 12/4.

  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area. 
  • The general trades contractor will commence drywall of the classroom wing stairwell
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue initial coats of level 1 classrooms
  • The painting contractor will continue initial coats of the level 2 corridors
  • The ceiling contractor will continue ceiling grid on level 1 C. 
  • The ceiling contractor will continue ceiling grid install in the level 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C classrooms
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 A
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechanical contractor will prepare for initial roof top unit deliveries in December
  • The electrical contractor will continue overhead and in wall rough-in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A light fixtures
  • The tile contractor will continue grouting of level 2 single bathrooms
  • The tile contractor will continue level 2 corridor tile
  • The metal windows contractor will continue installation of the lobby skylights
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge
Previous Article Project Update - Week of November 27th, 2023
Next Article Saturday Work - December 9th, 2023
Print
74 Rate this article:
No rating

Theme picker