Jonathan May / Monday, November 27, 2023 / Categories: Uncategorized Project Update - Week of November 27th, 2023 Please see the below project update and list of activities scheduled for the week of 11/27. The general trades contractor will continue metal framing activities in the cafeteria and kitchen The generla trades contractor will continue drywall activities on level 1 A, Lobby and admin area. The general trades contractor will continue taping level 1 area D The general trades contractor will continue insulation and drywall installation of the project areas and stair D The painting contractor will continue initial coats of level 1 classrooms The panting contractor will prime and paint the Platform exposed structure The painting contractor will continue priming of the gym CMU The ceiling contractor will continue ceiling grid on level 1 C. The ceiling contractor will commence ceiling grid install in the level 2 area C corridor The millwork and casework contractor will commence casework installation on level 2 area C classrooms The fire protection contractor will continue overhead rough in of the cafeteria and platform The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation insulation install The mechanical contractor will continue VAV duct connections on level 1 D and A The mechanical contractor will continue setting radiant panels into completed ceiling grid The electrical contractor will continue overhead rough-in on level 1 area B cafeteria The electrical contractor will continue installation of level 2 area c light fixtures The electrical contractor will commence installation of level 2 area d light fixtures The electrical contractor will commence level 2 toilet room light fixture install The tile contractor will continue installation of level 2 single bathrooms The elevator contractor will continue installation and assist other trades work within the elevator pit The metal windows contractor will continue installation of the translucent panel in the gym and over the lobby The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge Previous Article Saturday Work - November 18th, 2023 Next Article Project Update - Week of December 4th, 2023 Print 174 Rate this article: No rating