Project Update - Week of February 5th, 2024

Please see the below project update and list of activities scheduled for the week of February 5th, 2024

  • The general trades contractor will continue hanging and taping of the Fire Pump room and the Lobby skylight soffits.
  • The general trades contractor will receive the level 2 door and hardware delivery. 
  • The resilient flooring contractor will continue flooring installation on level 1 area C classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue ceiling grid install of the level 1 staff and student bathrooms. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will commence level 1 area D classroom casework installation.
  • The millwork and casework contractor will continue level 2 corridor cubby installation.
  • The millwork and casework contractor will continue window sill installation on level 2.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation. 
  • The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 2. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The electrical contractor will continue installation and wiring of level 1 admin area and media center light fixtures
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 1 area corridor tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The gym equipment contractor will commence overhead gym equipment installation.
Previous Article Project Update - Week of January 29th, 2024