Jonathan May / Friday, February 2, 2024 / Categories: Uncategorized Project Update - Week of February 5th, 2024 Please see the below project update and list of activities scheduled for the week of February 5th, 2024 The general trades contractor will continue hanging and taping of the Fire Pump room and the Lobby skylight soffits. The general trades contractor will receive the level 2 door and hardware delivery. The resilient flooring contractor will continue flooring installation on level 1 area C classrooms. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center. The ceiling contractor will continue ceiling grid install of the level 1 staff and student bathrooms. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will commence level 1 area D classroom casework installation. The millwork and casework contractor will continue level 2 corridor cubby installation. The millwork and casework contractor will continue window sill installation on level 2. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 2. The mechanical contractor will continue setting radiant panels into completed ceiling grid. The electrical contractor will continue installation and wiring of level 1 admin area and media center light fixtures The electrical contractor will continue fire alarm finish installation on level 1. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The tile contractor will continue level 1 area corridor tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The gym equipment contractor will commence overhead gym equipment installation. Previous Article Project Update - Week of January 29th, 2024 Next Article Saturday Work - February 3rd, 2024 Print 202 Rate this article: No rating