Jonathan May / Friday, January 26, 2024 / Categories: Uncategorized Project Update - Week of January 29th, 2024 Please see the below project update and list of activities scheduled for the week of January 29th, 2024 The general trades contractor will continue hanging and taping drywall in the Platform, Cafeteria, and Kitchen. The general trades contractor will complete hanging and taping drywall in the Stair A. The resilient flooring contractor will continue flooring installation on level 2 area A. The resilient flooring contractor will commence flooring installation on level 1 area C classrooms. The painting contractor will continue painting the level 1 admin area and lobby. The painting contractor will continue painting the gym ceiling. The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 area C classroom casework installation. The millwork and casework contractor will commence level 1 area D classroom casework installation. The millwork and casework contractor will continue level 2 corridor cubby installation. The millwork and casework contractor will continue window sill installation on level 2. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 2. The mechanical contractor will continue setting radiant panels into completed ceiling grid. The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. The electrical contractor will continue wiring of the level 2 corridor and level 1 classroom light fixtures. The electrical contractor will continue fire alarm finish installation on level 2. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The tile contractor will continue level 2 corridor tile. The tile contractor will continue level 1 area C corridor tile. The tile contractor will continue level 1 group bathroom tile. Previous Article Project Update - Week of January 22nd, 2024 Next Article Project Update - Week of February 5th, 2024 Print 183 Rate this article: No rating