Jonathan May
/ Categories: Uncategorized

Project Update - Week of July 22nd, 2024

Please see the below project update and list of activities scheduled for the week of July 22nd, 2024

  • The demolition of the existing FloRo will continue with the 1950s wings. 
  • The site contractor will continue granite curb installation at the bus and parent drop off loops. 
  • The site contractor will be finalizing installation of the south retaining wall. 
  • The site contractor will be setting grade of the parent drop off entrance road and pave initial binder course. 
  • The concrete contractor will continue forming and reinforcing of the remaining bus and parent drop of loop concrete areas. 
  • The project will conduct initial pre-inspection walk throughs ahead of final occupancy inspections. 
  • All contractor's will continue addressing punchlist items. 
Previous Article Project Update - Week of July 15th, 2024
Next Article Saturday Work - July 20th, 2024
Print
61 Rate this article:
5.0

Theme picker