Jonathan May / Saturday, July 20, 2024 / Categories: Uncategorized Project Update - Week of July 22nd, 2024 Please see the below project update and list of activities scheduled for the week of July 22nd, 2024 The demolition of the existing FloRo will continue with the 1950s wings. The site contractor will continue granite curb installation at the bus and parent drop off loops. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road and pave initial binder course. The concrete contractor will continue forming and reinforcing of the remaining bus and parent drop of loop concrete areas. The project will conduct initial pre-inspection walk throughs ahead of final occupancy inspections. All contractor's will continue addressing punchlist items. Previous Article Project Update - Week of July 15th, 2024 Next Article Saturday Work - July 20th, 2024 Print 113 Rate this article: 5.0