Jonathan May / Monday, July 15, 2024 / Categories: Uncategorized Project Update - Week of July 15th, 2024 Please see the below project update and list of activities scheduled for the week of July 15th, 2024 The demolition & abatement contractor has completed abatement of all ACM from the existing FloRo The demolition of the existing FloRo will continue with the 1960s & 50s wings. The site contractor will be completing initial paving of the bus loop entrance road. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road. The site contractor will continue setting curb for the entrance roads. The concrete contractor will commence forming and reinforcing of the remaining entrance concrete. The project will conduct final MEP inspections and NFPA 72 testing. All contractor's will continue addressing punchlist items. Previous Article Project Update - Week of July 8th, 2024 Next Article Project Update - Week of July 22nd, 2024 Print 122 Rate this article: 5.0