Jonathan May
/ Categories: Uncategorized

Project Update - Week of July 15th, 2024

Please see the below project update and list of activities scheduled for the week of July 15th, 2024

  • The demolition & abatement contractor has completed abatement of all ACM from the existing FloRo
  • The demolition of the existing FloRo will continue with the 1960s & 50s wings. 
  • The site contractor will be completing initial paving of the bus loop entrance road. 
  • The site contractor will be finalizing installation of the south retaining wall. 
  • The site contractor will be setting grade of the parent drop off entrance road. 
  • The site contractor will continue setting curb for the entrance roads. 
  • The concrete contractor will commence forming and reinforcing of the remaining entrance concrete. 
  • The project will conduct final MEP inspections and NFPA 72 testing. 
  • All contractor's will continue addressing punchlist items. 
Previous Article Project Update - Week of July 8th, 2024
Next Article Project Update - Week of July 22nd, 2024
Print
74 Rate this article:
5.0

Theme picker