Jonathan May / Saturday, July 6, 2024 / Categories: Uncategorized Project Update - Week of July 8th, 2024 Please see the below project update and list of activities scheduled for the week of July 8th, 2024 The demolition & abatement contractor has completed abatement of all interior spaces and will continue abatement of the roof. The demolition & abatement contractor will continue demolition of the existing FloRo Area C. The site contractor will continue subgrade preparation of all pavement areas. The site contractor will continue final grade setting in new pavement areas. The site contractor will commence layout and setting of granite curb. The concrete contractor will continue forming and reinforcing of the middle school sidewalk area and the loading dumpster pad. The painting contractor will continue painting of exterior rails. The millwork and casework contractor will continue installation of the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming and pre-functional testing. All contractor's will continue addressing punchlist items. Previous Article Saturday Work - June 29th, 2024 Next Article Project Update - Week of July 15th, 2024 Print 131 Rate this article: 4.2