Jonathan May / Friday, June 21, 2024 / Categories: Uncategorized Project Update - Week of June 24th, 2024 Please see the below project update and list of activities scheduled for the week of June 24th, 2024 The demolition contractor will continue abatement of the existing FloRo area B & A. The demolition contractor will continue disposal of the modular unit demolition material. The site contractor will continue infiltration system installation now that the south modular unit has been demolished. The site contractor will continue subgrade preperation of all pavement areas. The concrete contractor will continue prepparing front entrance concrete walks. The painting contractor will continue painting of exterior rails and structural steel. The millwork and casework contractor will continue installation of the media center desk and the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming. All contractor's will continue addressing punchlist items. Previous Article Project Update - Week of June 17th, 2024 Next Article Saturday Work - June 22nd, 2024 Print 137 Rate this article: 5.0