Project Update - Week of June 24th, 2024

Please see the below project update and list of activities scheduled for the week of June 24th, 2024

  • The demolition contractor will continue abatement of the existing FloRo area B & A. 
  • The demolition contractor will continue disposal of the modular unit demolition material. 
  • The site contractor will continue infiltration system installation now that the south modular unit has been demolished. 
  • The site contractor will continue subgrade preperation of all pavement areas. 
  • The concrete contractor will continue prepparing front entrance concrete walks. 
  • The painting contractor will continue painting of exterior rails and structural steel. 
  • The millwork and casework contractor will continue installation of the media center desk and the exterior benches. 
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The MEP contractors will continue system pre-functional testing of the kitchen equipment. 
  • The electrical contractor will continue final system programming. 
  • All contractor's will continue addressing punchlist items.