Project Update - Week of June 17th, 2024

Please see the below project update and list of activities scheduled for the week of June 17th, 2024

  • The demolition contractor will mobilize to site and commence site preperation activities. 
  • GELD will complete final disconnection of the existing FloRo's electrical service. 
  • The site contractor will commence subgrade preperation of the front entrance pavement areas. 
  • The site contractor will commence existing asphalt stripping of scheduled new pavement areas. 
  • The landscape contractor will continue installation of the kindergarten playground surface.
  • The landscape contractor will complete the building phase irrigation system coodination.  
  • The concrete contractor will commence forming of misc. front entrance concrete walks. 
  • The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. 
  • The painting contractor will continue painting of exterior rails and structural steel. 
  • The millwork and casework contractor will continue installation of the media center desk and the exterior benches. 
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The MEP contractors will continue system pre-functional testing of the kitchen equipment. 
  • The electrical contractor will continue final system programming. 
  • The carpet contractor will continue carpet installation in the vestibules. 
  • The project's Architect, Studio G Architects, will continue completing the punchlist of level 1 area B. Currently completed all of level 2 and level 1 areas A,C,&D. 
  • All contractor's will commence addressing punchlist items. 