Jonathan May / Saturday, June 15, 2024 / Categories: Uncategorized Project Update - Week of June 17th, 2024 Please see the below project update and list of activities scheduled for the week of June 17th, 2024 The demolition contractor will mobilize to site and commence site preperation activities. GELD will complete final disconnection of the existing FloRo's electrical service. The site contractor will commence subgrade preperation of the front entrance pavement areas. The site contractor will commence existing asphalt stripping of scheduled new pavement areas. The landscape contractor will continue installation of the kindergarten playground surface. The landscape contractor will complete the building phase irrigation system coodination. The concrete contractor will commence forming of misc. front entrance concrete walks. The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. The painting contractor will continue painting of exterior rails and structural steel. The millwork and casework contractor will continue installation of the media center desk and the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming. The carpet contractor will continue carpet installation in the vestibules. The project's Architect, Studio G Architects, will continue completing the punchlist of level 1 area B. Currently completed all of level 2 and level 1 areas A,C,&D. All contractor's will commence addressing punchlist items. Previous Article Project Update - Week of June 10th, 2024 Next Article Project Update - Week of June 24th, 2024 Print 123 Rate this article: 5.0