Jonathan May / Friday, March 8, 2024 / Categories: Uncategorized Project Update - Week of March 11th, 2024 Please see the below project update and list of activities scheduled for the week of March 11th, 2024 The general trades contractor will continue installation of level 2 and commence level 1 doors and hardware. The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. The general trades contractor will frame & drywall the main stair knee wall ahead of floor finishes. The resilient flooring contractor will continue the level 2 corridor flooring. The painting contractor will continue final painting of the level 2 area C classrooms. The ceiling contractor will continue cafeteria and kitchen ceiling installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 admin area casework install. The millwork and casework contractor will commence the stem patio cubby installation. The plumbing contractor will continue level 1 classroom sink installation. The plumbing and mechanical contractor will continue installing valve tags on level 2. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue installing the cafeteria wall diffusers. The mechanical contractor will install the gym fan blades. The electrical contractor will continue installation of the lobby and kitchen light fixtures. The electrical contractor will commence energizing electrical panels supported by permenant power. The electrical contractor will continue fire alarm finish installation on level 1. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will commence the cafeteria wall tile. The specialties contractor will continue installation of the toilet partitions. The site contractor will commence courtyard sitework preperation. The waterproofing and masonry contractor will re-mobilize to close in the project's level 2 loadout elevation. The misc. metals contractor will commence installation of the main stair railings. Previous Article Project Update - Week of March 4th, 2024 Next Article Saturday Work - March 9th, 2024 Print 180 Rate this article: No rating