Project Update - Week of March 11th, 2024

Please see the below project update and list of activities scheduled for the week of March 11th, 2024

  • The general trades contractor will continue installation of level 2 and commence level 1 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. 
  • The general trades contractor will frame & drywall the main stair knee wall ahead of floor finishes. 
  • The resilient flooring contractor will continue the level 2 corridor flooring. 
  • The painting contractor will continue final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue cafeteria and kitchen ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The millwork and casework contractor will commence the stem patio cubby installation. 
  • The plumbing contractor will continue level 1 classroom sink installation. 
  • The plumbing and mechanical contractor will continue installing valve tags on level 2. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue installing the cafeteria wall diffusers. 
  • The mechanical contractor will install the gym fan blades. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will commence energizing electrical panels supported by permenant power. 
  • The electrical contractor will continue fire alarm finish installation on level 1. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will commence the cafeteria wall tile.
  • The specialties contractor will continue installation of the toilet partitions. 
  • The site contractor will commence courtyard sitework preperation. 
  • The waterproofing and masonry contractor will re-mobilize to close in the project's level 2 loadout elevation. 
  • The misc. metals contractor will commence installation of the main stair railings. 