Jonathan May / Friday, March 1, 2024 / Categories: Uncategorized Project Update - Week of March 4th, 2024 Please see the below project update and list of activities scheduled for the week of March 4th, 2024 The general trades contractor will continue installation of level 2 doors and hardware. The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. The resilient flooring contractor will commence the level 2 area D corridor flooring. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The painting contractor will continue final painting of the level 2 area C classrooms. The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, cafeteria, and lobby. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation. The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will commence level 1 classroom sink installation. The plumbing contractor will continue final plumbing connections in the Mechanical Room. The plumbing and mechanical contractor will continue installing valve tags on level 2. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue installing the cafeteria wall diffusers. The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. The electrical contractor will continue fire alarm finish installation on level 1. The electrical contractor will continue making final electrical wiringing connections in the main electric room. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. Previous Article Project Update - Week of February 26th, 2024 Next Article Project Update - Week of March 11th, 2024 Print 193 Rate this article: No rating