Jonathan May / Friday, May 10, 2024 / Categories: Uncategorized Project Update - Week of May 13th, 2024 Please see the below project update and list of activities scheduled for the week of May 13th, 2024 The site contractor will continue preperation of the perimeter front concrete subgrade and setting of light pole bases. The concrete contractor will continue forming and pouring of the front entrance concrete. The landscape contractor will continue spreading of loam and layout of trees and shrubs. The landscape contractor will continue installation of the kindergarten playground. The misc. metals contractor will continue the installation of the exterior rails. The waterproofing contractor will continue exterior expansion joint caulking. The general trades contractor will continue framing of the stem patio ceiling. The resilient flooring contractor will continue the level 1 lobby flooring. The painting contractor will continue final painting of level 1. The ceiling contractor will continue installation of ceiling tiles. The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. The plumbing contractor will continue final connections of kitchen equipment. ALL MEP contractor's will continue final connections to the food service equipment. The mechanical contractor will continue with equipment commissioning. The controls contractor will continue integrating equipment into the building management system. The controls contractor will commense building commissioning. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet accessories and partitions. The shade contractor will continue shade installation in the level 1 classrooms. Previous Article Project Update - Week of April 22nd, 2024 Next Article Project Update - Week of May 20th, 2024 Print 162 Rate this article: 5.0