Jonathan May / Friday, May 17, 2024 / Categories: Uncategorized Project Update - Week of May 20th, 2024 Please see the below project update and list of activities scheduled for the week of May 20th, 2024 The concrete contractor will continue forming and pouring of the front entrance concrete. The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. The landscape contractor will continue installation of the kindergarten playground. The misc. metals contractor will continue the installation of the exterior rails. The waterproofing contractor will continue exterior expansion joint caulking. The resilient flooring contractor will continue the level 1 lobby flooring. The painting contractor will continue final patching and painting of level 1. The ceiling contractor will continue installation of ceiling tiles on level 2. The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. The plumbing contractor will be setting hot water valves at all sinks. The mechanical contractor will continue with equipment commissioning of the building's hot water system. The mechanical contractor will continue balancing the supply and return air system. The controls contractor will continue integrating equipment into the building management system. The controls contractor will commense building commissioning. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The fire protection contractor will commence sprinkler head install in the stem patio ceiling. The electrical contractor will commence stem patio light installation. The electrical contractor will commence security system programming. The specialties contractor will continue installation of the toilet accessories and partitions. Previous Article Project Update - Week of May 13th, 2024 Next Article Project Update - Week of May 27th, 2024 Print 157 Rate this article: 5.0