Please see the below project update and list of activities scheduled for the week of November 4th, 2024.

  • The landscape contractor will continue fence installation, final irrigation connections & programming, and commence hydroseeding the perimeter lawn areas. 
  • The electrical contractor will wire and set the entrance light pole. 
  • The concrete contractor will form and pour the remaining perimeter concrete walks. 