Jonathan May / Monday, October 28, 2024 / Categories: Uncategorized Project Update - Week of October 28th, 2024 Please see the below project update and list of activities scheduled for the week of October 28th, 2024 The site contractor will continue with the construction entrance re-establishment. The site contractor will continue with entrance road utility frame and cover adjustments ahead of final paving. The landscape contractor will commence placing sod, continue fence installation, and continue irrigation installation. Previous Article Project Update - Week of October 21th, 2024 Next Article Project Update - Week of November 4th, 2024 Print 101 Rate this article: No rating