Jonathan May / Friday, October 13, 2023 / Categories: Uncategorized Project Update - Week of October 16th, 2023 Please see the below project update and list of activities scheduled for the week of 10/16. The site contractor will continue the Outdoor Learning Lab subgrade preperation of concrete walkways. The masonry contractor will continue masonry install at the courtyard bumpouts. The window contractor will continue storefront installation. The metal panel contractor will continue the main canopy metal panel ceiling installation and the front entrance metal wall panel. The general trades contractor will continue interior metal framing and soffit erection on level 1 area A & B. The general trades contractor will continue in-wall blocking on level 1 area A. The general trades contractor will continue drywall and taping on level 1 C & D. The painting contractor will continue painting on level 2 area A and Level 1 area C. The ceiling contractor will continue ceiling grid install on level 2 area C and area D. The fire protection contractor will continue sprinkler overhead rough-in on level 1 area A & B. The fire protection contractor will commence the outdoor stem patio fire protection system. The plumbing contractor will continue in-wall rough in on level 1 area A. The plumbing contractor will complete the kitchen underslab piping. The mechanical contractor will continue tie-in of the level 1 area D VAVs. The mechanical contractor will continue in-wall duct insulation in level 1 A. The mechanical contractor will continue radiant heat panel installation in the level 2 area A. The mechanical contractor will continue setting radiant panel into ceiilng grid on level 2 Area D & A. The mechanical contractor will continue radiant heat panel final valve connections on level 2. The electrical contractor will continue main electric room buildout. The electrical contracotr will continue temporary power runs to the mechanical and elevator rooms. The electrical contractor will commence light fixture install on level 2 Area C Mock-up room. The elevator contractor will continue elevator installation. The tile contractor will continue level 2 C & D group bathroom floor and wall tile. Previous Article Saturday Work - October 14th, 2023 Next Article Saturday Work - October 21, 2023 Print 231 Rate this article: No rating