Jonathan May / Friday, September 8, 2023 / Categories: Uncategorized Project Update - Week of September 11th, 2023 Please see the below project update and list of activities scheduled for the week of 9/11. The site contractor will commence subgrade preperation of the loading dock ramp and stairs. The roofing contractor will continue installation of the canopy roofing and the metal roof edge. The masonry contractor will continue masonry install at the courtyard bump outs. The window contractor will continue installation of windows on level 1 area B. The window contractor will continue waterproofing of installed windows on level 1 area C &D. The metal panel contractor will continue metal panel installation of the low roof translucent panel perimeter. The general trades contractor will continue interior metal framing on level 1 area A. The general trades contractor will continue interior insulation on level 2. The general trades contractor will continue gypsum board installation on level 2 area A and level 1 area C & D The general trades contractor will continue taping on level 2 area D & A. The general trades contractor will continue buildout of the telecommunciations rooms. The painting contractor will commence painting of level 2 area C & D. The concrete contractor will continue preperation of the loading dock ramp and stairs. The concrete contractor will pour the platform and stair B landing stairs. The fire protection contractor will continue sprinkler rough in on level 1 area A. The plumbing contractor will continue in-wall rough in on level 1 Area D & A. The plumbing contractor will continue pipe insullation on level 2 A and level 1 C. The plumbing contractor will continue installation of the cafeteria canopy roof drains. The plumbing and mechanical contractor will continue buildout of the mechanical room. The mechanical contractor will continue installation of the level 2 VAVs. The mechanical contractor will continue duct insulation on level 1 area D and C. The electrical contractor will continue buildout of the electric rooms. The electrical contractor will continue overhead rough in in the gym and cafeteria. The electrical contracotr will continue telecommunications room buildout. The electrical contractor will continue in-wall rough in on level 1 area D. Previous Article Saturday Work - August 26th, 2023 Next Article Project Update - Week of September 18th, 2023 Print 227 Rate this article: No rating