Project Update - Week of September 11th, 2023

Please see the below project update and list of activities scheduled for the week of 9/11.

  • The site contractor will commence subgrade preperation of the loading dock ramp and stairs. 
  • The roofing contractor will continue installation of the canopy roofing and the metal roof edge. 
  • The masonry contractor will continue masonry install at the courtyard bump outs. 
  • The window contractor will continue installation of windows on level 1 area B.
  • The window contractor will continue waterproofing of installed windows on level 1 area C &D. 
  • The metal panel contractor will continue metal panel installation of the low roof translucent panel perimeter. 
  • The general trades contractor will continue interior metal framing on level 1 area A. 
  • The general trades contractor will continue interior insulation on level 2. 
  • The general trades contractor will continue gypsum board installation on level 2 area A and level 1 area C & D
  • The general trades contractor will continue taping on level 2 area D & A. 
  • The general trades contractor will continue buildout of the telecommunciations rooms. 
  • The painting contractor will commence painting of level 2 area C & D. 
  • The concrete contractor will continue preperation of the loading dock ramp and stairs. 
  • The concrete contractor will pour the platform and stair B landing stairs. 
  • The fire protection contractor will continue sprinkler rough in on level 1 area A. 
  • The plumbing contractor will continue in-wall rough in on level 1 Area D & A. 
  • The plumbing contractor will continue pipe insullation on level 2 A and level 1 C. 
  • The plumbing contractor will continue installation of the cafeteria canopy roof drains. 
  • The plumbing and mechanical contractor will continue buildout of the mechanical room. 
  • The mechanical contractor will continue installation of the level 2 VAVs. 
  • The mechanical contractor will continue duct insulation on level 1 area D and C. 
  • The electrical contractor will continue buildout of the electric rooms. 
  • The electrical contractor will continue overhead rough in in the gym and cafeteria. 
  • The electrical contracotr will continue telecommunications room buildout. 
  • The electrical contractor will continue in-wall rough in on level 1 area D. 