Jonathan May / Thursday, September 14, 2023 / Categories: Uncategorized Project Update - Week of September 18th, 2023 Please see the below project update and list of activities scheduled for the week of 9/18. The site contractor will commence subgrade preperation of the outdoor learning lab concrete walks. The masonry contractor will continue masonry install at the courtyard bump outs. The window contractor will continue installation of windows on level 1 area B. The window contractor will continue waterproofing of installed windows on level 1 area C &D. The window contractor will commence installation of exterior storefronts. The metal panel contractor will continue metal panel installation of the low roof translucent panel perimeter and the area A west bumpout. The general trades contractor will continue interior metal framing on level 1 area A. The general trades contractor will continue in-wall blocking on level 1 area A. The general trades contractor will commence interior insulation on level 1 area C. The general trades contractor will continue gypsum board installation on level 2 area A and level 1 area C & D The general trades contractor will continue taping on level 2 area A. The general trades contractor will continue buildout of the telecommunciations rooms. The painting contractor will continue painting of level 2 area C & D. The fire protection contractor will continue sprinkler rough in on level 1 area A. The plumbing contractor will continue in-wall rough in on level 1 Area D & A. The plumbing contractor will continue pipe insullation on level 2 A and level 1 C. The plumbing contractor will continue installation of the cafeteria canopy roof drains. The plumbing and mechanical contractor will continue buildout of the mechanical room. The plumbing contractor will commence kitchen underground installation. The mechanical contractor will continue installation of the level 2 VAVs. The mechanical contractor will continue duct insulation on level 1 area D and C. The mechanical contractor will commence radiant heat panel installation in the level 2 area C classrooms. The electrical contractor will continue buildout of the electric rooms. The electrical contractor will continue overhead rough in in the gym and cafeteria. The electrical contractor will continue in-wall rough in on level 1 area A. The electrical contractor will commence classroom overhead fixture accessory installation on level 2 area C. The electrical contractor will continue telecommunications room buildout. Previous Article Project Update - Week of September 11th, 2023 Next Article Saturday Work - September 16th, 2023 Print 231 Rate this article: No rating