Project Update - Week of September 16th, 2024

Please see the below project update and list of activities scheduled for the week of September 16th, 2024

  • The site contractor will continue setting final grade of the front lawn area. 
  • The site contractor will continue setting light pole bases and excavation of site lighting conduit paths on the north side of the lawn area. 
  • The electrical contractor will continue site lighting conduit install and wiring. 
  • The landscape contractor will continue the front area play equipment installation. 