Jonathan May
/ Categories: Uncategorized

Saturday Work - November 4th, 2023

The project will be working on the site this Saturday 11/4/23. Activities will consist of the following:

  • The plumbing contractor will continue level 1 A rough-in & insulation
  • The mechanical contractor will continue VAV connections on level 1 C
  • The electrical contractor will continue lighting control rough-in on level 2. 
Previous Article Project Update - Week of October 23rd, 2023
Next Article Project Update - Week of November 6th, 2023
Print
101 Rate this article:
No rating

Theme picker