Jonathan May / Thursday, October 5, 2023 / Categories: Uncategorized Saturday Work - October 7th, 2023 The project will be working on the site this Saturday 10/7/23. Activities will consist of the following: The electrical contractor will continue overhead light fixture control installation on level 2 A. The plumbing contractor will continue level 1 area A in-wall rough-in. Previous Article Project Update - Week of October 10th, 2023 Next Article Saturday Work - October 14th, 2023 Print 226 Rate this article: No rating