Jonathan May / Friday, September 22, 2023 / Categories: Uncategorized Saturday Work - September 23rd, 2023 The project will be working on the site this Saturday 9/23/23. Activities will consist of the following: The site contractor will commence kitchen underground plumbing excavation The plumbing contractor will continue gas pipe installation to the kitchen. The plumbing contractor will continue in-wall rough in on level 1 area D. The electrical contractor will continue lighting control rough in on level 2 area C & D. Previous Article Project Update - Week of Septemer 25th, 2023 Next Article Project Update - Week of October 2. 2023 Print 224 Rate this article: No rating