Project Update - Week of July 25th 2022

Tripp McElroy III 0 343 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 7/25.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week.     
  • The site contractor shall continue with the installation of drainage piping and structures in the utility corridor between the existing Florence Roche and Middle School South buildings. 
  • Prep and proof rolling of the native subgrade at the existing athletic field location shall continue next week.  Delivery and placement of structural fill materials within the footprint of the new building shall continue this week in this same location.      

Saturday Work - July 23rd 2022

Tripp McElroy III 0 369 Article rating: No rating

The project will be working on the site this Saturday 7/23/22. Activities will consist of the following: 

  • The site contractor shall continue with stripping/removing the asphalt materials located at the existing track.  Removal and stockpiling of the existing sub-grade materials below the track shall be done in conjunction with the asphalt stripping/removal activity.

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

Project Update - Week of July 18th 2022

Tripp McElroy III 0 347 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 7/18.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week.  
  • Continue with the installation of drainage piping and setting of drainage structures on the South elevation of the new athletic field.       
  • The site contractor shall continue with the installation of drainage piping and structures in the utility corridor between the existing Florence Roche and Middle School South buildings. 
  • Prep and proof rolling of the native subgrade at the existing athletic field location shall continue next week.  This supports the delivery and placement of structural fill materials within the footprint of the new building also located at the existing athletic field location.      

Project Update - Week of July 11th 2022

Tripp McElroy III 0 360 Article rating: 1.7

Please see the below project update and list of activities scheduled for the week of 7/11.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week. 
  • Continue construction of the retaining wall #7 adjacent to the new athletic track.  The retaining wall block materials shall continue to be delivered to the site next week. 
  • Continue with the installation of drainage piping and setting of drainage structures in the new athletic field.       
  • The site contractor shall continue with the installation of drainage piping and structures in the utility corridor between the existing Florence Roche and Middle School South buildings. 
  • A series of material deliveries are scheduled for the project site next week including but not limited to crushed stone to support retaining wall construction and drainage structures.

Project Update - Week of July 4th 2022

Tripp McElroy III 0 400 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 7/4.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week. 
  • Continue subgrade prep and construction of the retaining walls adjacent to the new athletic track.  The retaining wall block materials shall continue to be delivered to the site next week. 
  • Continue with the installation of drainage piping and setting of drainage structures in the new athletic field.       
  • The site contractor shall commence and continue with the installation of drainage piping and structures in the utility corridor between the existing Florence Roche and Middle School South buildings. 
  • A series of material deliveries are scheduled for the project site next week including but not limited to crushed stone to support retaining wall construction and drainage structures.
  • Due to the holiday on Monday 7/4 there will not be any work activities on the project site.  Happy Independence Day! 