Saturday Work - August 12th 2023 The project will be working on the site this Saturday 8/12/23. Activities will consist of the following: Tripp McElroy III / Thursday, August 10, 2023 0 252 Article rating: No rating The window contractor shall continue with the installation of perimeter foam and sealant details at the windows in Area C-Level 2. The general trades contractor shall be insulating the exterior walls in Area C-Level 2 and framing & sheathing the walls of the Main Mechanical room. The electrical contractor shall continue with in-wall rough-in in Area A-Level 2 and Area C-Level 1. The plumbing contractor shall continue with in-wall rough-in in Area C-Level 1. This weekend work schedule has been communicated and coordinated with the Town Manager's Office. Read more
Saturday Work - July 29th 2023 The project will be working on the site this Saturday 7/29/23. Activities will consist of the following: Tripp McElroy III / Thursday, July 27, 2023 0 214 Article rating: No rating The window contractor shall continue with window installation on the South elevation of Area D. The general trades contractor shall continue with setting of door frames and installation of in-wall blocking on Level 2 of Area C. The site contractor shall backfill and prep the subgrade around the electrical vault in the Main Electrical room. The electrical contractor shall complete the underground rough-in to the electrical vault in the Main Electrical room. This trade shall also continue with in-wall rough-in on Level 2 of Area D. The plumbing contractor shall continue with the installation of gas piping in the mechanical room. The mechanical contractor shall continue layout and coordination of the mechanical piping in the mechancial room. The mechanical contractor shall continue with overhead duct installation on Level 1 of Area D. Read more
Project Update - Week of July 3rd 2023 Please see the below project update and list of activities scheduled for the week of July 3rd 2023 Tripp McElroy III / Friday, June 30, 2023 0 234 Article rating: No rating Placement of the slab on grade in the gymnasium and lobby area is tentatively scheduled for Thursday 7/6 or Friday 7/7 weather dependant. The general trades contractor will continue exterior framing & sheathing in Areas A & B. The general trades contractor will continue layout and interior framing on level 2 Areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas C & D and commence installation on Areas A & B. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will commence installation of fire protection pipe on Level 1 Area C. The window contractor will commence with installation of the metal windows on Area C of the building. The project will be closed on Tuesday 7/4 due to the holiday. Read more
Project Update - Week of June 12th, 2023 Please see the below project update and list of activities scheduled for the week of June 12th 2023 Tripp McElroy III / Friday, June 9, 2023 0 238 Article rating: No rating The concrete contractor shall commence with the preperation of the Slab on Grades in Area A and Gymnasium of the building. Concrete placement of Stairs A & D are tentatively scheduled for next week. The misc metals contractor is scheduled to deliver and commence erection of Stair C. The general trades contractor will continue exterior framing in areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and commence in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will continue installation of fire protection pipe on Level 2 Area D. Read more
Project Update - Week of May 22nd 2023 Please see the below project update and list of activities scheduled for the week of May 22nd 2023 Tripp McElroy III / Friday, May 19, 2023 0 252 Article rating: No rating The general trades contractor will continue layout, framing & sheathing of exterior walls on the 1st & 2nd levels of Areas C & D. The general trades contractor shall continue with layout and commence top track installation of interior wall framing on the 2nd levels of Areas C & D. The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and continue with the installation of ductwork & mechanical piping. The plumbing contractor will continue with the lay-out and installation of plumbing piping on the second level of Areas C & D of the building. The electrical contractor shall continue with the installation of temp power and lighting provisions on the first level of Areas A & B of the building. The electrical contractor shall continue with in-wall electrical rough-in at the gymnasium CMU walls. The electrical contractor shall continue with the overhead rough-in of electrical feeders on the second level of Areas C & D of the building. The fire protection contractor shall commence with overhead rough-in of sprinkler piping on the second level of Area C. The masonry contractor shall continue construction of the CMU walls in the gymnasium. The masonry shall continue with masonry veneer starter course on Area C of the building. Masonry veneer activites on the exterior mock-up shall continue next week. The waterproofing contractor shall continue with the installation of the waterproofing membrane on the exterior walls of Areas C & D of the building. Read more