Saturday Work - August 12th 2023

The project will be working on the site this Saturday 8/12/23. Activities will consist of the following:

Tripp McElroy III 0 279 Article rating: No rating
  • The window contractor shall continue with the installation of perimeter foam and sealant details at the windows in Area C-Level 2.
  • The general trades contractor shall be insulating the exterior walls in Area C-Level 2 and framing & sheathing the walls of the Main Mechanical room.
  • The electrical contractor shall continue with in-wall rough-in in Area A-Level 2 and Area C-Level 1.
  • The plumbing contractor shall continue with in-wall rough-in in Area C-Level 1.

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

Saturday Work - July 29th 2023

The project will be working on the site this Saturday 7/29/23. Activities will consist of the following:

Tripp McElroy III 0 235 Article rating: No rating
  • The window contractor shall continue with window installation on the South elevation of Area D.
  • The general trades contractor shall continue with setting of door frames and installation of in-wall blocking on Level 2 of Area C.
  • The site contractor shall backfill and prep the subgrade around the electrical vault in the Main Electrical room.
  • The electrical contractor shall complete the underground rough-in to the electrical vault in the Main Electrical room.  This trade shall also continue with in-wall rough-in on Level 2 of Area D.
  • The plumbing contractor shall continue with the installation of gas piping in the mechanical room. 
  • The mechanical contractor shall continue layout and coordination of the mechanical piping in the mechancial room. 
  • The mechanical contractor shall continue with overhead duct installation on Level 1 of Area D. 

Project Update - Week of July 3rd 2023

Please see the below project update and list of activities scheduled for the week of July 3rd 2023

Tripp McElroy III 0 258 Article rating: No rating
  • Placement of the slab on grade in the gymnasium and lobby area is tentatively scheduled for Thursday 7/6 or Friday 7/7 weather dependant. 
  • The general trades contractor will continue exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D and commence installation on Areas A & B. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will commence installation of fire protection pipe on Level 1 Area C. 
  • The window contractor will commence with installation of the metal windows on Area C of the building.
  • The project will be closed on Tuesday 7/4 due to the holiday.

Project Update - Week of June 12th, 2023

Please see the below project update and list of activities scheduled for the week of June 12th 2023

Tripp McElroy III 0 264 Article rating: No rating
  • The concrete contractor shall commence with the preperation of the Slab on Grades in Area A and Gymnasium of the building.
  • Concrete placement of Stairs A & D are tentatively scheduled for next week.
  • The misc metals contractor is scheduled to deliver and commence erection of Stair C. 
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and commence in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 2 Area D.

Project Update - Week of May 22nd 2023

Please see the below project update and list of activities scheduled for the week of May 22nd 2023

Tripp McElroy III 0 272 Article rating: No rating
  • The general trades contractor will continue layout, framing & sheathing of exterior walls on the 1st & 2nd levels of Areas C & D. 
  • The general trades contractor shall continue with layout and commence top track installation of interior wall framing on the 2nd levels of Areas C & D.
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and continue with the installation of ductwork & mechanical piping.
  • The plumbing contractor will continue with the lay-out and installation of plumbing piping on the second level of Areas C & D of the building. 
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the first level of Areas A & B of the building.
  • The electrical contractor shall continue with in-wall electrical rough-in at the gymnasium CMU walls.
  • The electrical contractor shall continue with the overhead rough-in of electrical feeders on the second level of Areas C & D of the building.
  • The fire protection contractor shall commence with overhead rough-in of sprinkler piping on the second level of Area C.
  • The masonry contractor shall continue construction of the CMU walls in the gymnasium. 
  • The masonry shall continue with masonry veneer starter course on Area C of the building.  Masonry veneer activites on the exterior mock-up shall continue next week.
  • The waterproofing contractor shall continue with the installation of the waterproofing membrane on the exterior walls of Areas C & D of the building. 
RSS
1345678910Last

Theme picker