Project Update - Week of September 5th 2022

Tripp McElroy III 0 381 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 9/5.  

  • The fencing contractor will commence with the fence installation on the West side of the new track and field. 
  • The electrical contractor will continue with the electrical work to support power to the new athletic field shed location.
  • The site contractor shall commence prepping and raking out the atheltic field loam in preparation for Sod materials to be delivered the week of 9/12.
  • The track surfacing contractor is scheduled to mobilize to the project site on Tuesday 9/6 and commence their pre-work inspection of the track surface.
  • The electrical and site contractors will continue the electrical ductbank installation towards the BESS system pad. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor shall continue with foundation insulation installation and back-filling activities in Areas C & D. 
  • The concrete contractor will continue and complete foundation construction for the classroom wings in Areas C & D. 
  • The site contractor will continue to excavate for foundations in Areas A & B. 
  • The contractor shall commence with the construction of footings in Area A.
  • The concrete contractor is scheduled to receive a rebar delivery for Area A on Wednesday 9/7 and Anchor Bolts for Area A on Friday 9/9.  
  • Concrete placements are tentatively scheduled for Wednesday 9/7 and Friday 9/9.
  • Due to the Labor Day holiday on Monday 9/5 there will not be any work activities onsite.

Project Update - Week of August 29th 2022

Jonathan May 0 348 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/29.

  • Exporting excess materials from the site shall continue this week.   
  • The fencing contractor will complete the athletic field retaining wall fence installation. 
  • The irrigation system will be completed
  • The drainage structure covers will be installed
  • The electrical contractor will commence providing power to the new athletic field shed location 
  • The concrete contractor will continue foundation construction for the classroom wings Area C & D. 
  • The site contractor will continue to excavate the Area A & B foundations. 
  • The electrical and site contractors will continue the electrical ductbank installation down Champney Street. 
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of August 22nd 2022

Tripp McElroy III 0 399 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 8/22.

  • Exporting excess materials from the site shall continue this week.   
  • Complete the construction of the long jump pits at the new track area. 
  • Commence the installation of the irrigation system in the new athletic field.
  • Continue with site restoration and re-establishment of the temporary construction fence line shall continue this week adjacent to the Middle School South building.   
  • The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank working South on the site towards Champney Street. 
  • The site contractor shall continue with excavation and subgrade prep for concrete foundations in Area A of the building.      
  • The site contractor shall continue importing and placing structural fill materials in Area B of the new building. 
  • The concrete contractor shall continue construction of foundation formwork in Area C  and commence in Area A of the new building.  Foundation wall construction shall commence in Area D of the new building.  Concrete placements are tentatively scheduled for Wednesday 8/24 and Friday 8/26 this week.  

Saturday Work - August 20th 2022

Tripp McElroy III 0 419 Article rating: No rating

The project has a street sweeper scheduled for Saturday 8/20 to sweep around the perimeter of the existing Florence Roche Elementary and Middle School South buildings where the underground utility work was completed this summer.     

Project Update - Week of August 15th 2022

Tripp McElroy III 0 394 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/15.

  • Exporting excess materials from the site shall continue this week.   
  • The site contractor shall continue placing the loam materials beneath the new athletic field.
  • The site contractor shall place the top coat of asphalt at the new Athletic Track area on Thursday 8/18. 
  • Prep and placement of the concrete track game pads shall continue this week.
  • Continue with site clean-up and subgrade prep to support asphalt placement at the utility trenches next week.  Asphalt placement is scheduled for Thursday 8/18 and Friday 8/19.  Site restoration and re-establishment of the temporary construction fence line shall commence this week adjacent to the Middle School South building.   
  • The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank work located in the utility corridor and continue towards Champney Street.        
  • The site contractor shall continue importing and placing structural fill materials in Areas A & B of the new building. 
  • The concrete contractor is scheduled to mobilize on Monday 8/15 and commence lay-out and construction of foundation formwork in Areas C & D of the new building.  The first concrete placement is tentatively scheduled for Thursday 8/18.  
  • The project is scheduled to receive a series of reinforcing steel deliveries on Tuesday 8/16 and Thursday 8/18 of this week to support foundation construction.     