Project Update - Week of October 11th 2022

Jonathan May 0 294 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 11th 2022. 

  • The athletic track line stripper will commence track markings. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas B.  
  • The site contractor will commence loading dock footing backfill. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will continue underslab plumbing excavation. 
  • The site contractor will prep and set the BESS system vault and transformer pad. 
  • The concrete contractor will continue forming and placing the loading dock and site wall foundation. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will continue layout and installation of the underslab plumbing in Area C.  

Project Update - Week of October 3rd 2022

Jonathan May 0 304 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 3rd 2022. 

  • The track surface contractor will continue the track surface installation
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of the Area B site wall, the loading dock, and the gym interior strip footing. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will begin building underslab plumbing excavation. 
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will begin forming and installing rebar for the loading dock deep footing. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will begin layout and installation of the underslab plumbing in Area C.  

Project Update - Week of September 26th 2022

Jonathan May 0 313 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 26th 2022. 

  • The track surface contractor will finalize layout and commence the track surface installation.
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of Area B. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.

 

Project Update - Week of September 19th 2022

Jonathan May 0 388 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 19th 2022. 

  • The irrigation with complete final position of irrigation heads. 
  • The track surface contractor will begin placing of the synthetic track surface. 
  • The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. 
  • The concrete contractor will continue forming and placing concrete foundations in Areas A & B.  
  • Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D.  
  • The site contractor will continue foundation excavation of Areas A & B. 
  • The site contractor will continue utility installation below the proposed perimeter access road.
  • The site contractor will continue various grading activities around the site. 

Town of Groton Special Town Meeting Information

Tripp McElroy III 0 396 Article rating: No rating

The Town of Groton Special Town Meeting is MONDAY, September 12, 2022 at 7:00 p.m. at the Groton Middle School Performing Arts Center

The purpose of the meeting is to request authorization to increase the borrowing for the Florence Roche Elementary School Project by $9.5 million.

 

To review the VIDEO OF THE INFORMATION SESSION (presented at the FRBC, last night, 09/08/22) please see the link below:

https://us02web.zoom.us/.../KlQBkfAldgZGXO7aYDZlGSIxVO0Kt...

Passcode: #4AZLdhK

 

For those with Kids - BABYSITTING IS AVAILABLE (6:30 PM until end of Meeting, Ages 5 thru 12) - SIGN UP BELOW:

https://docs.google.com/.../1bAjArPe839hJpimQ9jzokQW.../edit

RSS
First2223242527293031Last

Theme picker