Jonathan May / Friday, December 29, 2023 / Categories: Uncategorized Project Update - Week of January 2nd, 2024 Please see the below project update and list of activities scheduled for the week of January 2nd, 2024 The general trades contractor will continue metal framing and hanging drywall in the Media Center, Lobby, and Cafeteria. The general trades contractor will continue hanging drywall of the Stair D The general trades contractor will continue taping level 1 area A & B as well as Stair C. The flooring contractor will continue resilient flooring on level 2 area C and commence the level 2 area D classrooms. The painting contractor will continue painting the level 1 classrooms and corridors The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors. The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms. The millwork contractor will receive the level 1 area C classroom casework and the level 2 corridor casework. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform The mechanical contractor will continue setting radiant panels into completed ceiling grid The mechanical contractor will commence final setting of the level 2 ceiling diffusers. The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. The tile contractor will continue level 2 corridor tile The tile contractor will continue level 1 group bathroom floor and wall tile preperation Previous Article Project Update - Week of December 26th, 2023 Next Article Project Update - Week of January 8th, 2024 Print 203 Rate this article: No rating