Jonathan May / Friday, January 12, 2024 / Categories: Uncategorized Project Update - Week of January 15th, 2024 Please see the below project update and list of activities scheduled for the week of January 15th, 2024 The general trades contractor will continue hanging and taping drywall in the Lobby, Cafeteria, and Kitchen. The general trades contractor will continue hanging and taping drywall in the Stair D. The resilient flooring contractor will continue flooring installation on level 2 area D and A. The painting contractor will continue painting the level 1 classrooms, corridors, and admin area. The ceiling contractor will continue ceiling grid installation on level 2 bathrooms and and level 1 classroom wings. The ceiling contractor will commence ceiling grid installation of the admin area. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 2. The millwork and casework contractor will continue level 1 area C classroom casework installation The millwork and casework contractor will continue level 2 corridor cubby installation The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation. The plumbing contractor will commence with level 2 classroom and bathroom sink installation. The plumbing contractor will commence final plumbing connections to mechanical equipment in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 2. The mechanical contractor will continue setting radiant panels into completed ceiling grid. The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. The electrical contractor will continue wiring of the level 2 corridor and level 1 classroom light fixtures. The electrical contractor will continue fire alarm finish installation on level 2. The tile contractor will continue level 2 corridor tile. The tile contractor will continue level 1 group bathroom floor and wall tile preperation. Previous Article Project Update - Week of January 8th, 2024 Next Article Project Update - Week of January 22nd, 2024 Print 170 Rate this article: No rating