Jonathan May
/ Categories: Uncategorized

Project Update - Week of January 22nd, 2024

Please see the below project update and list of activities scheduled for the week of January 22nd, 2024

  • The general trades contractor will continue hanging and taping drywall in the Platform, Cafeteria, and Kitchen.
  • The general trades contractor will complete hanging and taping drywall in the Stair D.
  • The general trades contractor will commence hanging and taping drywall in Stair A. 
  • The resilient flooring contractor will continue flooring installation on level 2 area A.
  • The painting contractor will continue painting the level 1 admin area. 
  • The painting contractor will commence painting the gym ceiling. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue ceiling grid installation of the level 1 bathrooms. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area C classroom casework installation.
  • The millwork and casework contractor will continue level 2 corridor cubby installation.
  • The millwork and casework contractor will continue window sill installation on level 2.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation.
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation. 
  • The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 2. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The mechanical contractor will continue unit heater installation in the entrance vestibules.
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The electrical contractor will continue wiring of the level 2 corridor and level 1 classroom light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 2.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 2 corridor tile. 
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 
Previous Article Project Update - Week of January 15th, 2024
Next Article Project Update - Week of January 29th, 2024
Print
65 Rate this article:
No rating

Theme picker